Progress Update #25

Date

Museum Construction Site Weekly Progress Update #25
  • Installing 4TH Rings on Mega Columns
  • Grouting of Mega Column Ring 4
  • Poured 3 Sections of Concrete Wall along Leadership Institute
  • Installing Wall Forms Along Admin/Workstation Wing
  • Installing Rebar for Concrete Walls along Mechanical Room
  • Installing Void Boxes and Waterproofing Membrane at Pour #5 – Rotunda
  • Excavating and Fine Grading for Pour #6 – Rotunda
  • Stripping Formwork for completed Pour #8
Overhead Drone Image
AT&T Stadium
Tower Crane at Night

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent