Weekly Progress Update #24:
- Installed 3rd rings on all mega columns.
- Poured 1st section of concrete wall at Leadership Institute.
- Installing wall forms at Theater.
- Installing rebar reinforcement for concrete walls along Workstations.
- Excavating vestibule recesses, fine grading and setting edge forms for pour #5.
- Installing void boxes, waterproofing and rebar pour #8.
- Installing MEP structural supports inside of all mega columns.
- Backfilling excavation of material lift pit.


If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent