Progress Update #23

Date

Museum Construction Site Weekly Progress Update #23

Weekly Progress Update #23:

  • Installation of 2nd rings on all mega columns.
  • Installing wall forms at Leadership Institute.
  • Installing rebar reinforcement for concrete walls along Workstations.
  • Excavating pier caps, fine grading and setting edge forms for pour #5.
  • Installing void boxes, waterproofing and rebar pour #8.
  • Completed chilled water lines and gas line to the building. 
Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent