Weekly Progress Update #26:
- Completed slab pour #8 concrete.
- Slab Pour #5 installing void boxes, waterproofing membrane, and rebar reinforcement.
- Wall pour #4 was completed and setting forms for pour #5.
- Installed all mega column ring 5’s and beginning to set 6’s.
- Slab Pour #6, fine grading, excavating pile caps / floor recesses and installing void boxes.
- Installed 6 piers at the new thickened slab area.



If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent