Weekly Progress Update #11:
- Utility Yard / Pump House: Oncor Gear has been energized/power on!! continued installing 12” insulated chilled water lines, continued installation of grade beams, temporary irrigation pump has been installed and connected.
- Installing Mega Column footings.
- Waterproofing Mega caps.
- Drilling remaining auger piles at the building and site walls.
- Installing tower crane footing and base of crane.
*You can see the outline of the Leadership Institute and Theater!