Weekly Progress Update #10:
- Utility Yard / Pump House: Installing secondary electrical conduits and service panels. Also, installing 12” insulated chilled water lines.
- Installing Mega Column footings.
- Excavating grade beams in Leadership Institute.
- Installing tower crane piers.


If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent