Weekly Progress Update #12:
- Installing mega cap footings #4 & #5.
- Waterproofing mega cap footings #2 & #3.
- De-energized and removed existing Oncor gear.
- Poured tower crane footing.
- Installed underground storm water lines.
- Excavated and formed grade beams.

If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent