Museum Construction Site Weekly Progress Update #24

Weekly Progress Update #24:

  • Installed 3rd rings on all mega columns.
  • Poured 1st section of concrete wall at Leadership Institute.
  • Installing wall forms at Theater.
  • Installing rebar reinforcement for concrete walls along Workstations.
  • Excavating vestibule recesses, fine grading and setting edge forms for pour #5.
  • Installing void boxes, waterproofing and rebar pour #8.
  • Installing MEP structural supports inside of all mega columns.
  • Backfilling excavation of material lift pit.
Overhead Drone Photo of Site
Up Close at Night With the Tower Crane

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent