Weekly Progress Update #18:
- Installation of underground and in-slab electric conduits in pour #2, #4, #5 and #10.
- Installation of underground sanitary sewer line in Pour #11 (Café/Kitchen).
- Installation of foundations at the pour #1 Leadership Institute, pour #2 Theater and pour #3 Workstations (ADMIN AREA).
- Installation of Primary electrical lines from the Oncor yard to the building.