Weekly Progress Update #17:
- Installation of underground electric conduits in pour #2, #3, #5, #10 & #11.
- Poured concrete at mega column stem wall #2
- Installation of foundations at the pour #1 Leadership Institute, pour #2 Theater and pour #3 Workstations (ADMIN SPACE).

If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent