Weekly Progress Update #19:
- Installation of underground electric conduits in pour #4, #6 and #10.
- Installation of underground sanitary sewer line in Pour #11 (Café/Kitchen).
- Poured Theater (Pour #2).
- Installation of foundations at the pour #3 Workstations and pour #4 mechanical rooms.
- Installation of passenger elevator pit.
- Installation of Primary electrical lines form Oncor yard to the building.


If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent