Museum Construction Site Weekly Progress Update #6

Weekly Progress Update #6:

  • Utility Yard / Pump House: Installing Utility Yard grade Beams and Pump House foundation.
  • Drilling auger cast piles in the Rotunda footprints. ( 272 total Piles drilled to date)
  • Beginning pier cap foundations in Leadership Theater.
Overhead Drone Photo 1 of Site
Overhead Drone Photo 2 of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent