Museum Construction Site Weekly Progress Update #5

Weekly Progress Update #5:

  • Utility Yard / Pump House: Set Switchgear pads, finished underground plumbing, final connection of 8” irrigation line.
  • Poured lake sidewalk section #2.
  • Drilling auger cast piles in the Stramp / Mechanical room footprints. ( 229 total Piles to date)
Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent