Weekly Progress Update #5:
- Utility Yard / Pump House: Set Switchgear pads, finished underground plumbing, final connection of 8” irrigation line.
- Poured lake sidewalk section #2.
- Drilling auger cast piles in the Stramp / Mechanical room footprints. ( 229 total Piles to date)