Progress Update #33

Date

Museum Construction Site Weekly Progress Update #33

 Weekly Progress Update #33:

  • Closing Wall Pour #15 forms.
  • Installing wall pour #13 & #14 rebar reinforcement.
  • Slab Pour #10A, completed
  • Installing Rotunda level structural steel.
  • Installing Knuckle columns on top of Mega columns 2 & 4.
  • Installing main electrical underground feeds to the building electrical rooms in pour #10B.

FUN FACT

Total yards of concrete poured on the entire job site to date is 6,865 yards which equals to 25,400,500 pounds of concrete.

Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent