Museum Construction Site Weekly Progress Update #32

 Weekly Progress Update #32:

  • Wall pour #11 concrete complete. 
  • Installing Wall Pour #15 wall forms and rebar.
  • Slab Pour #10A, Installing waterproofing, Rebar reinforcement and Electrical conduit.
  • Installing structural steel at Administration Area and Theater Vestibule.
  • Installing main electrical underground feed to the building electrical rooms.

INTERESTING INFORMATION

W&W | AFCO Steel is our fabricator and supplier.  You may be aware of a few of their projects: 

AT&T Stadium – 15,000 tons of steel

Globe Life Field – 21,000 tons of steel

Dickies Arena – 2,500 tons of steel

National September 11th Memorial and Museum – 1,500 tons of steel

The steel you see below was purchased from Nucor, Arkansas.  The National Medal of Honor Museum will have nearly 3,000 tons of structural steel that was fabricated in San Angelo and Abilene, Texas with 73 Veterans on Staff!!!  ‘Merica!

Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent