Weekly Progress Update #2:

  • 1st concrete paving pour completed.
  • Installed curb forms and rebar for new driveway 2nd concrete pour. Concrete pour scheduled for 5:00am this Thursday morning. ( 170 cubic yards of concrete )
  • Utility Yard / Pump House: underground utilities are being installed. Oncor electrical lines for new transformers and switch gear finishing this week, installing 10”  intake line that feeds from the lake to the pump house for irrigation.
  • Installed formwork and rebar at lake sidewalk.
Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent