Progress Update #1

Date

Museum Construction Site Weekly Progress Update #1

 Weekly Progress Update #1

  • Installed curb forms and rebar for new driveway. Concrete pour scheduled for 3:00am this Friday morning. ( 300 cubic yards of concrete )
  • Utility Yard / Pump House: underground utilities are being installed. (4” gas line, Oncor electrical lines for new transformers and switch gear, sewer lines and lake intake line to pump house for irrigation.
  • Building foundation. Auger Cast Piers being drilled. ( 163 piers drilled to date )
  • New 15” underground storm line being installed around the building. (Approximately 15’ deep)
Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent