Museum Construction Site Weekly Progress Update #22

Weekly Progress Update #22:

  • Installation of 1st ring of mega column #1.
  • Pour #4 completed
  • Installing rebar reinforcement for concrete walls in Leadership Institute.
  • Completed passenger elevator waterproofing and back filled. 
  • Excavating grade beams and pier caps, fine grading and setting edge forms at Amphitheater Lobby pour and Rotunda.
Overhead Drone Photo of Site
Medal of Honor Recipients Construction Site Visit on 3 November 2022. 
From L to R, Donald ‘Doc’ Ballard, Bruce Crandall, MG Patrick ‘Pat’ Brady, Michael ‘Mike’ Fitzmaurice. 

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent