Weekly Progress Update #16:
- Installation of underground sanitary sewer and storm lines in the building.
- Installation of underground electric in pour #2 (Theater)
- Poured concrete at mega column stem walls 3, 4 & 5
- Installation of foundations at the pour #1 Leadership Institute, pour #2 Theater and pour #3 Workstations (ADMIN AREA).
If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent