Museum Construction Site Weekly Progress Update #10

Weekly Progress Update #10:

  • Utility Yard / Pump House:  Installing secondary electrical conduits and service panels.  Also, installing 12” insulated chilled water lines.
  • Installing Mega Column footings.
  • Excavating grade beams in Leadership Institute.
  • Installing tower crane piers.
Overhead Drone Photo 1 of Site / Overall Site
Overhead Drone Photo 2 of Site / Utility Yard/Pump House