Weekly Progress Update #6:
- Utility Yard / Pump House: Installing Utility Yard grade Beams and Pump House foundation.
- Drilling auger cast piles in the Rotunda footprints. ( 272 total Piles drilled to date)
- Beginning pier cap foundations in Leadership Theater.


If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent