Progress Update #4

Date

Museum Construction Site Weekly Progress Update #4

Weekly Progress Update #4:

  • 3rd concrete paving pour completed. (170 yards)
  • Utility Yard / Pump House:  Pouring transformer pads, underground plumbing installs ongoing.
  • Form and Rebar Lake sidewalk #2.
  • Drilling auger cast piles in the Leadership Theater footprint. ( 212 total Piles to date)
  • Built up subgrade for Entry Stramp.
Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent