Weekly Progress Update #37:
- Detailing Structural Steel.
- Welding Off Mega Column Knuckle Columns.
- Installing edge forms and excavating grade beams and pier caps for Slab Pour 10B.
- Wall Pour 13B Concrete Completed.
- Slab Pour 13A concrete completed.
FUN FACT
We have approximately 19,000 cubic yards of dirt stockpiled up at the laydown yard, all this material was excavated from the building site and about 7,000 cubic yards will be reused for back filling around the building and site walls.