Museum Construction Site Weekly Progress Update #36

Weekly Progress Update #36:

  • Detailing Structural Steel.
  • Welding Off Mega Column Knuckle Columns.
  • Installing Electrical Underground In Main Electrical Room Slab Pour 10B.
  • Wall Pour 14 Concrete Completed.
  • Wall Pour 13A Closing Wall Forms to get ready for concrete pour.
  • Slab Pour 13A Installing Waterproofing and Void Boxes.
  • Demobilizing Crawler Crane.

STEEL KNUCKLE COLUMN WEIGHT

There are five (5) steel knuckle columns.  Each steel knuckle column weighs 18,000 lbs.

Steel Knuckle Columns 