Progress Update #20

Date

Museum Construction Site Weekly Progress Update #20
  • Installation of underground electric conduits in pour #5, #8.
  • Installation of underground sanitary sewer lines in Pour #10 & #11 (Café/Kitchen/Back of House).
  • Installation of insulation board and drainage mat around poured grade beams.
  • Installation of foundations at the pour #3 Workstations and pour #4 mechanical rooms. 
  • Installation of passenger elevator pit walls.
  • Installation of Primary electrical lines from Oncor yard to the building.
Overhead Drone Image
Overhead Drone Image
Tower Crane at Night

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent