Progress Update #61

Date

Museum Construction Site Bi-Weekly Progress Update #61

Overview/Project Accomplishments:

  • Installing roof cladding support system.
  • Installing Rotunda roof waterproofing system.
  • Installing exterior sheathing on the Great Hall.
  • Installed metal decking and reinforcement for pour #3 Exhibit Hall floor.
  • Poured concrete baffle walls in the Theater.
  • Poured the Great Hall concrete topping slab.
  • Continue installing overhead MEPF throughout the building.
  • Installing CMU walls in the back of house / loading dock area.
  • Interior wall framing ongoing throughout the building.
Overhead Drone Photo of Site

Waterproofing

We have taken the first steps in constructing the event/parade lawns that surround the museum.  The lawns will serve as a ‘green roof’ over the Rotunda level building areas.   More than 40,000sf (roughly one acre) of waterproofing (see picture 2) has been installed by Centennial Moisture Control of Irving, TX.  Next steps will include a combination of geofoam and earthen fill to support natural vegetation.

Waterproofing (looking from the Admin Area out to the main entrance of the Museum on AT&T Way)

Question:  Can you identify the mega column in this picture? 

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent