Progress Update #60

Date

Museum Construction Site Bi-Weekly Progress Update #60

Overview/Project Accomplishments:

  • Exhibit Hall floor pours 1 & 2 completed.
  • Completed Exhibit Hall Roof Decking.
  • Installing roof cladding support structure.
  • Installing CMU around pump house.
  • Great Hall glass installed.
  • Theater glass install ongoing.
  • Interior Rotunda level Wall Framing Ongoing.
  • Installing Overhead MEPF conduits, duct & pipe Throughout the Rotunda.
  • Rotunda roof waterproofing beginning.
  • Great Hall fireproofing and exterior wall framing complete.
Overhead Drone Photo of Site

Glass Panes in the Great Hall

  • The beautiful, full-height glass panes that are used in both the Great Hall and the Leadership Theater are oversized units made in Steyr, Austria by Vandaglas. 
  • Each double-laminated pane is 23 feet tall, 7 wide, and weighs 2,200 lbs. 
  • Each tall pane is stabilized by triple-laminated glass “fins” that are 23 feet tall x 1’2” wide . 
  • The total assembly of glass in each end wall weighs more than 11 tons.
Glass Panes in the Great Hall     
View from the Exhibit Deck in the early morning hours of Monday, September 11th, 2023 (Patriot Day) *Notice the Topping Out Beam*

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent