Progress Update #42

Date

Museum Construction Site Weekly Progress Update #42

Overview/Project Accomplishments:

  • Crane Pad installation on West side of building. 
  • Installing waterproofing and backfilling behind building foundation walls.
  • Installing metal decking over the Administration Area. 
  • Passenger elevator hydraulic pistons completed.
  • Structural Steel installation back of house/loading dock areas. 
  • Welding steel caps at top of columns in prep for disk bearing install.
  • Concrete completed for lower stramp walls.
  • Forming and placing rebar for the 1st upper stramp wall pour.
Overhead Drone Photo of Site

DID YOU KNOW?

There is a St. Michael’s Medallion in each of the five (5) foundations under the Mega Columns.  St. Michael, the patron saint of warriors, is often represented as an angelic warrior, fully armed with helmet, sword, and shield.  St. Michael is also viewed as a protector.   

President & CEO Chris Cassidy placing the St. Michael’s Medallion in the foundation under the Mega Column in 2022.

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent

Share

Subscribe today.
Get the Insider updates delivered directly to your inbox!

More articles