Progress Update #40 – Overview/Project Accomplishments:

  • Wall Pour #12 & #13A Set forms and rebar reinforcement.
  • Installing Café Structural Steel.
  • Welding Knuckle Columns Steel caps on the Mega Columns.
  • Completed metal decking at the Institute & Theater.
  • Installing site storm water lines.
  • Installing waterproofing and back filling building retaining walls.
  • Installing Passenger elevator Hydraulic Jacks.
  • Installed Cooling Towers at the utility yard.
  • Grading stramp and installing storm & electrical lines.
Overhead Drone Photo of Site

Mega-Column Steel Pedestal Cap Plates

The Mega-Column Steel Pedestal Cap Plates have been installed.  These caps are approximately 10-inches thick and weigh 5,000 pounds.  They will ‘cap’ the tops of the Mega-Columns and will support the entire 200 x 200 Exhibition Level Structure (and part of the staircases).  The ‘dead load’ (empty deck) of the Exhibition Level is over 10,000,000 pounds. 

Mega-Column Steel Pedestal Cap Plate  

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent

Share

Subscribe today.
Get the Insider updates delivered directly to your inbox!

More articles