Progress Update #40 – Overview/Project Accomplishments:
- Wall Pour #12 & #13A Set forms and rebar reinforcement.
- Installing Café Structural Steel.
- Welding Knuckle Columns Steel caps on the Mega Columns.
- Completed metal decking at the Institute & Theater.
- Installing site storm water lines.
- Installing waterproofing and back filling building retaining walls.
- Installing Passenger elevator Hydraulic Jacks.
- Installed Cooling Towers at the utility yard.
- Grading stramp and installing storm & electrical lines.

Mega-Column Steel Pedestal Cap Plates
The Mega-Column Steel Pedestal Cap Plates have been installed. These caps are approximately 10-inches thick and weigh 5,000 pounds. They will ‘cap’ the tops of the Mega-Columns and will support the entire 200 x 200 Exhibition Level Structure (and part of the staircases). The ‘dead load’ (empty deck) of the Exhibition Level is over 10,000,000 pounds.

If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent