Overview/Project Accomplishments:
- Poured the remaining concrete foundation for the Great Hall.
- Framing and sheathing the exterior of the Theater.
- Installing the Theater glass anchor systems and mullions.
- Installation of both Spiral Stairs ongoing.
- Exhibit Hall floor metal decking installation ongoing.
- Exhibit Hall roof – completed the bolting and welding of structural steel.
- Demobilized the 800-ton crane (THE BEAST) from the site.

NMOHM Upcoming Milestones
We’re thrilled to share some exciting news with you regarding our ongoing progress at the National Medal of Honor Museum Construction Site. As we continue to make progress, we’re approaching several milestones that mark key stages in our journey.
Here are the upcoming milestones to look forward to:
- Milestone 1: Spiral Staircase Installation/Completion (Now until 30 September 2023)
- Milestone 2: Rotunda Level Glass Enclosure Installation/Completion (Now until end of February 2024)
- Milestone 3: Exhibit Hall Exterior Wall Cladding Installation/Completion (15 February 2024 to 31 August 2024)
- Milestone 4: Flagpole Installation/Completion (September 2024)
We appreciate your continued support and enthusiasm as we work towards completing this project. Stay tuned for more updates and details on these very exciting milestones.




If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent