Weekly Progress Update #21:
- Installation of underground electric conduits in pour #6, #7.
- Installation of underground chill water line to building.
- Prepping to begin installation of building concrete walls on South end of Leadership Institute.
- Installation of foundations at the pour #4 mechanical room and pour #8 amphitheater lobby.
- Completed concrete at passenger elevator pit walls and began waterproofing.
- Erection of crawler crane for installation of mega columns (FYI, crane is erected in the location of the Great Hall (formerly the Hall of Valor)).


If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent