Progress Update #17

Date

Museum Construction Site Weekly Progress Update #17

Weekly Progress Update #17:

  • Installation of underground electric conduits in pour #2, #3, #5, #10 & #11.
  • Poured concrete at mega column stem wall #2
  • Installation of foundations at the pour #1 Leadership Institute,  pour #2 Theater and pour #3 Workstations (ADMIN SPACE). 
Overhead Drone Photo of Site

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent