Weekly Progress Update #15:
- Completed the utility yard foundations.
- Installed the grease trap.
- Installation of underground sanitary sewer and storm lines in the building.
- Installation of underground electric in pour #1(Leadership Institute) & pour #2 (Leadership Theater)
- Forming and rebar reinforcement for mega column stem walls
- Installation of foundations at the Leadership Institute and Leadership Theater.



If you would like to view a time lapse picture of the site, please use the link below:
https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent