Weekly Progress Update #14:
- Tower crane erected.Installing underground electric conduit in Leadership Institute.
- Demoed pump foundation and well.
- Installing underground sanitary sewer lines and storm lines in mechanical room North side of the Stramp.
- Forming mega column base curbs and installing MEP sleeves.
- Poured storage room concrete slab.
- Installed forms and rebar reinforcement for cooling tower slab.
- Back filled Mega cap footings 4 & 5.
- Excavating and forming pier caps.