Progress Update #39

Date

Museum Construction Site Weekly Progress Update #39

Progress Update #39 – Overview/Project Accomplishments:

  • Slab pour #10B Concrete complete.
  • Wall Pour #11B Set forms and rebar reinforcement.
  • Installing Café Structural Steel.
  • Welding Knuckle Columns Steel caps on the Mega Columns.
  • Installing metal decking on top of structural steel.
  • Installing site storm water lines.
  • Installing waterproofing and back filling building retaining walls.
Overhead Drone Photo of Site

DID YOU KNOW?

As part of the 2022 Groundbreaking Ceremony, soil from all 50 states was ceremoniously deposited into the Museum site.  This gesture symbolized our nation’s gratitude to Medal of Honor Recipients and the country’s support for the National Medal of Honor Museum as it honors and tells their stories.  The idea and all the hard work that went into making this possible is attributed to my extremely talented colleague, Jennifer Surgalski. 

‘Is all of this just dirt?  Maybe.  But in these places, it represents so much more.  The grounds of battle are made hallowed by the blood and sweat poured out into the dirt.’

                              -Jake Tapper statement at the 2022 Groundbreaking Ceremony

Soil being deposited on site by Medal of Honor Recipients during the 2022 Groundbreaking Ceremony

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent

Share

Subscribe today.
Get the Insider updates delivered directly to your inbox!

More articles