Progress Update #68

Date

Museum Construction Site Bi-Weekly Progress Update #68

Overview/Project Accomplishments:

  • Installing MEP overhead and wall rough-in throughout the Rotunda.
  • Framing interior and exterior walls on the Exhibit Hall.
  • Installing exterior wall framing clips on the Exhibit Hall.
  • Installing Sheathing on the exterior walls of the Exhibit Hall South elevation.
  • Prepping for install of Rotunda skylight glass beams.
  • Installing elevator glass.
  • Caulking exterior sheathing joints for waterproofing system.
  • Installing roof parapet walls on the Exhibit Hall.

DANTE TISI SITE VISIT

Buenos Dias from Argentina!  This week we traveled to Buenos Aires to review the completed panels, in process fabrication, and conduct a test “fit up” and installation training at the Dante Tisi plant.  Dante Tisi will begin delivering panels to the jobsite at the end of February.  The images below show one completed panel (+/- 150 lbs.) of the 3930 panels that will be used to clad the Exhibition Hall.  The mockup was used to test the installation process which will include a crane to support the panel while 4 persons (in boom lifts) align and install each panel.

Completed Panel
Mockup used to test the installation process
Jose Cavazos, Linbeck Senior Project Manager, briefing the Dante Tisi Team

If you would like to view a time lapse picture of the site, please use the link below:

https://oxblue.com/pro/slideshow/nationalmedalofhonormuseum/mostrecent