Progress Update #65

Date

Museum Construction Site Bi-Weekly Progress Update #65

Overview/Project Accomplishments:

  1. Installing MEPF overhead inside of the Great Hall and Education wing.
  2. Installing cable and column brackets for the installation of the elevator glass.
  3. Installing exterior wall and interior wall tracks on the Exhibit Hall.
  4. Exhibit Hall Light weight concrete roof system completed.
  5. Installing roof vapor barrier system on the Exhibit Hall roof.
  6. Completed the last concrete pour on the Exhibit Hall floor.
  7. Completed the spray foam insulation on the underside of the Exhibit Hall floor.
  8. Fireproofing spray ongoing around the exterior of the Exhibit Hall.
  9. Theater mezzanine concrete floor poured, and wall framing began.
  10. 85-ton crawler crane will arrive next week to begin the glass installation of the elevators in the Rotunda.
Picture 1:  Overhead Drone Photo of Site
Picture 2:  Overhead Drone Photo of Site