Progress Update #28

Date

Museum Construction Site Weekly Progress Update #28
  • Completed slab pour #6 concrete.
  • Slab Pour #7 installing void boxes, waterproofing membrane, and rebar reinforcement.
  • Wall pour #6 installing forms and rebar reinforcement.
  • Slab Pour #11, setting edge forms, fine grading, excavating pile caps & L-beams.
  • Preparing anchor bolts and embeds for structural steel delivery (Steel Delivery on 19 December 2022).