Progress Update #59

Date

Museum Construction Site Bi-Weekly Progress Update #59

Overview/Project Accomplishments:

  • Pour Concrete roof deck on Great Hall.
  • Installing Exhibit Hall Roof Decking.
  • Installing Electrical Floor Boxes & conduit on Exhibit Hall floor.
  • Installing Spiral Stairs (Ongoing).
  • Installing CMU around pump house.
  • Installing Great Hall glass framing system.
  • Interior Rotunda level Wall Framing (Ongoing).
  • Installing Overhead MEPF conduits, duct & pipe throughout the Rotunda.
Overhead Drone Photo of Site

Exhibition Hall Concrete Pour

Get ready for more concrete!   

Approximately 500 yards of concrete will be poured at the Exhibition Hall floor on 11 September with a second pour tentatively scheduled on 15 September. 

Due to the way the structure is designed to move during construction (structure sequencing), the North-East and South-West quarters will be poured first (in orange, Area ‘A’).  Our teammates from Linbeck are self-performing the work.

Exhibition Hall Concrete Pour Sequence

If you would like to view a time lapse picture of the site, please use the link below:

https://insider.mohmuseum.org/live